TC Energy says Coastal GasLink Phase 2 proceeds after LNG Canada expansion FID
Bitget2026/09/29 10:31- TC Energy will proceed with Coastal GasLink Phase 2 following LNG Canada’s positive final investment decision on its expansion.
- Phase 2 targets a near-doubling of Coastal GasLink’s 2.1 Bcf/d capacity via added compressor stations and facility upgrades.
- LNG Canada will run construction as execution manager; Coastal GasLink stays owner, operator, permit holder, limiting capital and cost overrun exposure.
- Construction is expected to start in early 2027; in-service targeted for the early 2030s.
- Project scope covers the existing 670-kilometer route from Dawson Creek to the LNG Canada facility in Kitimat, British Columbia.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Yemen's Houthis vow more attacks on Saudi airports, oil facilities

Yen slips to a three-week low on US CPI, then recovers it all

Inflation surpasses expectations, impacting small-cap stocks; Russell 2000 drops nearly 2%, confirming a technical correction
On Wednesday, approximately four-fifths of the constituents in the Russell 2000 Index recorded declines. Since its peak in August, the index has dropped by 11%, falling below its 200-day moving average and entering a technical correction for the first time since March this year. Analysis indicates that with the US CPI rising more than expected and the probability of rate hikes increasing, small-cap, consumer, and transportation stocks are facing "sustained and long-term resistance."